Highway 11 Paving And Grading Work Is Slightly Behind

Highway 11 construction is slightly behind schedule with paving and grading work.

Ministry of Transportation Ontario Environmental Planner Andrew Healy says the current construction on Highway 11 will see it’s paving and grading work completed a month later than expected.

Healy says the paving and grading being done on the highway from Hyundai Road heading eastbound should be complete by the end of July, rather than the previously predicted end of June.

He says due to the abnormal amount of wet weather that has hit the area over the spring and early summer, the paving process has been slowed down.

Healy says this current portion of the project is still on schedule to be completed by the end of September, crews will then break before resuming in May of 2018.

Nick Birnie
Nick Birnie
Motivated Journalist/Broadcaster who is accomplished in research, interviewing and reporting with advanced knowledge of newsroom computer systems. Focused, successful in developing articles, short stories, editorial pieces and broadcast scripts (voiceovers, on-cam, reports). Strong command of the English language and familiar with a wide range of writing styles.

Continue Reading

ckap Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

ONTC announces new direct route between Thunder Bay, Hearst and Timmins

New route will also connect to Northlander in Porcupine.

Nishnawbe Aski Police-led drug investigation ends with major seizure

$4.358-million of drugs and $315,000 in cash, in addition to 15 firearms and five vehicles. 

New Dialysis Unit at Sensenbrenner Hospital in Kapuskasing officially opens

New unit serves about 16 patients from Smooth Rock Falls to as far west as Constance Lake.

Union going public trying to get Extendicare to the bargaining table

Members of the Canadian Union of Public Employees who work for Extendicare at its seniors care facilities cannot legally go strike.

Notre Dame Hospital foundation hopeful fundraising is completed following this year’s radiothon

Moose FM Community Cares Radiothon is Friday, Dec. 11 raising money for Notre Dame Hospital Foundation in Hearst and the Sensenbrenner Hospital Foundation in Kap.
- Advertisement -